A press brake might take three minutes to form a bracket once the tooling is in place. For a ten-piece order, that gives you 30 minutes of run time. If installing the tooling and checking a trial bend takes another 30 minutes, the forming operation needs an hour. An estimate based on the three-minute cycle alone would miss half the operation time.

When you estimate a fabrication quote, record setup time and run time separately for each operation. Then check how many times the shop will need to set up for the quantity and release schedule you’re pricing.

What belongs in setup time?

Setup is the work you do to get an operation ready to run. At a press brake, that might include installing tooling, loading the program, adjusting the backgauge and checking a trial bend. If the setup has to be torn down and rebuilt for a later release, include the time for each setup the shop expects to repeat.

Run time covers the work repeated during production. For the bracket, it can include loading and positioning the blank, making the bends, and unloading and stacking the part. If a dimension check happens once every ten pieces, estimate that check at the rate it occurs. Keep each activity in one place so the same work gets counted once.

How to calculate batch time

For an operation with the same setup duration each time, use this formula.

Total operation time = (number of setups × minutes per setup) + (pieces run × minutes per piece)

Divide total operation time by the number of finished pieces quoted to get the average time per finished piece. If you expect to run extra blanks for tryout or scrap, estimate the time those blanks use and divide by the quantity you plan to deliver. Count any trial work you already included in setup just once.

A worked example for a bracket order

Assume 30 minutes per press-brake setup, including a separate trial bend, and three minutes of run time per finished bracket. The numbers are fictional. Each bracket has the same bends and runs at the same pace. There’s one setup per release in this example.

Estimated press-brake time by order plan
Order planSetupsSetup timeRun timeTotal forming timeAverage per piece
10 in one run130 min30 min60 min6 min
40 in one run130 min120 min150 min3.75 min
40 in two runs260 min120 min180 min4.5 min

Going from 10 to 40 in one run spreads the same setup over more brackets. A second setup adds 30 minutes back to the 40-piece estimate. If the customer wants two shipments and the shop can form all 40 brackets in one run, the estimate may still use one forming setup. Price any packaging, storage or delivery work the split adds.

What to check before pricing the job

  • List the setup and run time separately for each operation, such as cutting, forming and welding. For processes that make several pieces per cycle, estimate the number of cycles required.
  • Check the routing for fixture changes, tool changes and runs that have to be split. Record the setup count behind each quantity option.
  • Add any work outside the basic cycle, such as periodic inspection, deburring or moving parts between work centers. Account for material, finishing and other costs separately.
  • Apply your shop’s appropriate rates to the time you’ve estimated. If your shop tracks operator and machine time separately, use each rate for the hours it covers.
  • Record the production assumption with the estimate. “40 pieces formed in one run” gives the reviewer a specific assumption to revisit if the order changes.

Once the operation costs are in place, see FabWerks’ worked example on fabrication cost versus selling price for the next step in building the quote.