A customer sends Rev C while you are pricing Rev B. The filenames look nearly identical, and the email only says “updated drawing.” Before you finish the quote, pin down which revision the price covers and what the new drawing changes for the shop.

Keep a record of the drawings you priced

Start with the drawing number, sheet and revision shown in the title block. Record the date you received the file and keep a copy of the package you used. The email date helps you trace the request. The drawing number and revision tell the next estimator which document you priced.

If the revision in the filename differs from the title block, ask the customer which one governs. With several drawings in a package, record the revision for each relevant sheet. A new assembly drawing can arrive while the detail drawings stay at their previous revisions.

Separate receiving a drawing from changing the estimate

When a replacement drawing comes in, compare it with the one the current estimate uses. Look for changes to dimensions, quantities, material, finishes and inspection requirements. Review related notes and detail sheets as well, especially where a change affects more than one part.

Say who will review the update and whether the current quote can proceed. A corrected sheet title may leave the estimate intact. A changed hole pattern can send the estimator back to programming, shop time or purchased parts. Capture the reason for keeping or revising the price so another person can follow the decision.

Work through a revision with a specific example

Suppose your shop priced 24 brackets from drawing B-117, Rev B. In this fictional example, Rev C adds two mounting holes to each bracket. The material and order quantity stay the same, but the shop needs to check whether the existing cutting program and inspection plan still work.

Record the change in plain language. “B-117 Rev C adds two mounting holes per bracket. Confirm programming and inspection before issuing the revised offer.” That note tells the next reviewer what changed, what remains open and why the old price needs a second look.

If the customer has already received the Rev B offer, keep a copy of that offer. When you send the updated quote, state that it prices B-117 Rev C and identify the earlier offer it replaces. Anyone comparing the two versions can then see which drawing each price covers.

Use this revision check before issuing the offer

  • Identify each drawing and sheet the estimate uses, including its revision.
  • Confirm unclear changes with the customer and record the response.
  • Check which material, shop operations, outside services or lead times the change affects.
  • Update the scope and price together, and identify any prior offer the update replaces.
  • Confirm which quote and drawing package the customer accepted before handing the work off to production.

When a drawing change raises an open question, keep the answer with the quote review. Read How to Review a Fabrication Quote Without Losing the Questions for a way to track those decisions.